Commons project calendar

Construction Zone Update

Proposed project schedule:

(updated August 15, 2013)

Proposed project schedule Start* - Finish*

The contract has been
awarded to Flintco Pacific, Inc.

    

 

 

    Expected completion

Phase 1:    

Site utilities and preparation

COMPLETED

Phase 2:    

Construction of South Building

COMPLETED

Phase 3:

Demolition of former Student
Services Building

COMPLETED

Phase 4:    

Construction of North Building

May 11, 2014

Phase 5:

Demolition of Cafeteria and
HRM Buildings

July 8, 2014

Phase 6:    

Construction of New Commons and
North Entry

January 5, 2015

* Phase dates are approximate and subject to change

 