| Proposed project schedule:
(updated January 16, 2013) |
||
| Proposed project schedule | Start* - Finish* | |
|
The contract has been |
||
|
|
|
|
| Expected completion |
||
|
Phase 1: |
Site utilities and preparation |
COMPLETED |
|
Phase 2: |
Construction of South Building |
COMPLETED |
|
Phase 3: |
Demolition of former Student |
January 28, 2013 |
|
Phase 4: |
Construction of North Building |
May 11, 2014 |
|
Phase 5: |
Demolition of Cafeteria and |
July 8, 2014 |
|
Phase 6: |
Construction of New Commons and |
January 5, 2015 |
* Phase dates are approximate and subject to change